As a follow on to A-CDM, the aim of this project is to provide Dublin Airport with a n Initial Airport Operations Plan to be made available to airport stakeholders to better manage the airport and enhance the passenger experience.

Scope
Improved Integrations
– Integration of ATC Flight Trajectory Data
– Integration of Meteorological Data

Improved predictability to make better use of airport resources and understand constraints. Improved decision making.
Share mandatory data with Network Manager
Landside Process possibility – Passenger Journey – Security, CBP, Boarding etc.
Budget
EUR 7.9 million
Status
Ongoing
Partners
Dublin Airport Operations
daa IT
Airlines/Handlers
IAA
Eurocontrol
Met provider
(more may be added as project progresses)
Location
Dublin Airport
Estimated date of termination
31/12/2023